Enable High Contrast Mode
Disable High Contrast Mode
June 6, 2022
This Contract with the Onteora Central School District included upgrades to the districts sports stadium, storm drainage systems and staff parking lot. Both our Site & Trenchless teams were involved in the project. The Site division installed an ACO trench drain along each side of the running track along with new goal posts and discus net foundations in the field. The Trenchless division lined the storm sewer pipe beneath the football field to avoid excavation and reconstructed the parking lot adjacent to the field. This site work was managed by Tom Petersen and Rian Baker & the lining work was managed by Matt Gardiner & Drew Wolff. The Field Superintendents were Barry Kaiser & Ben Felshaw. The contract was valued at $492,568.