October 3, 2025
This contract with SUNY New Paltz was for the reconstruction of the North Turf Field. This project included demolition and removal of the existing running track, turf field and fencing to make way for a new 2 lane running track, new turf playing surface, new press box and bathroom facility. Other work included electrical upgrades performed by J&J Sass Electric Inc, new storm drainage system, new water service lines, new concrete bleacher pads, poured foundations for the new press box and bathroom building. The Turf Field Was installed by Chenango Contracting Inc. The Track Coating was Installed by American Athletic Track and Turf. The Press Box was manufactured and installed by Dant Clayton. The Restroom building was prefabricated and set onsite by M&W Precast. This project completed in May 2025 was managed by Tom Petersen and Rian Baker. The Superintendent was Tom Petersen Jr. The concrete Superintendent was Jon Auer. This project was valued at $3,918,783.00.